Under Refresh Sub-assembly it is now possible to replan sub-assemblies at different levels

The Refresh Sub-assembly function has been improved. A pop-up will now be displayed, where you have the following options:

  • Refresh option: This allows you to refresh the planning at different levels (current sub-assembly, sub-assembly incl. underlying) with changes in the production order.